Thread: Time Calculation

  1. #1

    Time Calculation



    Register for a FREE account, and/
    or Log in to avoid these ads!

    Project Start Time 22-04-2015 12:30:00
    Project End Time 24-04-2015 20:30:00

    Shift Start Time 11:00:00
    Shift End Time 21:30:00

    The total time spent on the project is 29 hours but a simple subtraction is not working and is giving me 56 hours as its taking time beyond Shift End Time 21:30:00.

    Any suggestions on how to get this regularized.

  2. #2
    Conjurer sambit's Avatar
    Join Date
    Sep 2014
    Posts
    143
    Articles
    0
    Excel Version
    Excel2007
    Hi,
    plz see the file.
    Attached Files Attached Files

  3. #3
    Assuming the start date & time is in A2, and the end date & time is in B2

    =(NETWORKDAYS(A2,B2)-1)*("21:30"-"11:00")
    +IF(NETWORKDAYS(B2,B2),MEDIAN(MOD(B2,1),"21:30","11:00"),"21:30")
    -MEDIAN(NETWORKDAYS(A2,A2)*MOD(A2,1),"21:30","11:00")